8 Inches Side Al Type Pressure Membrane Shell Side Nozzle Installation Instructions

Article Source: This Site Release Date:2018-12-29


1. The side gate installation accessories are: stainless steel side gate, sealing ring, ring gasket, stainless steel fastening screw Hat; Lubricant adopts glycerol or household detergent, see below.


2. Before installation of the membrane shell side gate, see below.


3. Install the sealing ring in stainless steel side gate seal groove, see below.


4. Pour a little glycerin or detergent on the sealing ring, lubricant, a finger will lubricant evenly daub on the sealing ring, see below.


5. Stainless steel side nozzle and membrane shell side nozzle must maintain the correct installation position (stainless steel side gate bottom steps the thinnest place, in the middle position) membrane shell side gate, see below.


6. Will install the sealing ring daub is the lubricant of the stainless steel side gate from inside the membrane shell lightly loaded membrane shell side gate, loads membrane shell side gate seal face must be careful not to scratch, less effort, make the stainless steel side gate installed (note: the stainless steel side nozzle must keep correct installation location), see below.


7. Plastic pad ring is installed on the side gate, see below.


8. With one hand inside the membrane shell pressure stainless steel side gate (avoid stainless steel side nozzle rotating), another hand will stainless steel fastening nut on the side gate, and then use hand tighten namely